Construction Projects

Construction Projects

Sugar House Construction Projects

Updated report

April 20, 2022

Sugarmont Apartments—Boulder Ventures

  • Start date: Fall of 2017.
  • Several tenants are occupying Phase I and Phase II, of the project. Leasing continues to move briskly. There will continue to be periodic disruptions on McClellan as large trucks continue to deliver materials and work on the west side of the building continues.

WB Sugarmont, between Highland Drive and McClelland, is now officially open but may experience periodic short-term closures to accommodate finishing work still being performed on the south side of the project. Flagmen will be on hand to assist traffic on these occasions.

  • completion: This year (2022) for sure, maybe. Keeping fingers crossed!
  • Location: Project borders Sugarmont and McClelland St.

Sugar Alley – Lowe Development

  • Start date: Fall 2020.
  • Update: Progress continues moving rapidly as the structure of the building has reached its full height and has filled in the block framed by Wilmington on the south and the Vue development to the north. A temporary pedestrian walkway is installed in the outside, southbound lane of Highland Drive from the north end of the project south to the Wilmington crossin. Highland Drive will be reduced to one lane SB, from just south of 2100 South to Wilmington. The new Wilmington extension, a private roadway, will be reduced to one-way traffic (east bound only) accessed from McClellan St. The two-lane access formerly connecting Highland Drive to McClellan St., also a private roadway, is now reduced to one lane, west bound, and will be permanently closed to vehicle traffic at the end of the project. This will be a five-story building containing 200 luxury apartments with the ground floor dedicated to retail, including restaurants and a bike shop.
  • completion: Mid 2022.
  • Project description: Mixed use residential.
  • Location: 2200 S. Highland Drive.

Westport Capital Project (former Shopko Site)

  • Start date: Summer 2017.
  • Update: The approximately 100-unit apartment building on the west side of the site is now nearly ready for occupancy. Finishing touches are being made to the lobby/reception area. The building is set to open soon.
  • completion (third phase): Early 2022.
  • Project description: U of U Medical Clinic/Commercial Office Space/Residential.
  • Location: Former Shopko site.

Izzy South & North

  • Start Date: Late January ’22.
  • Update: Excavation work has been begun on both the north and south sites. Foundations are now formed on the north site. A permit is being issued to allow for the closure of the outside, WB lane on 2100 S., between 500/600 East, to accommodate utility installations for the Izzy North project. This closure will exist for approximately 5-6 weeks and will begin before the end of the April. The traffic shift will begin just west of the 700 East intersection, opening back up just before the 500 East intersection.
  • Completion: Fall of ’23.
  • Project description: 2-70+ unit residential, townhomes and single floor, with small commercial component on west end, ground floor.
  • Project Location: 550 E./2100 S.

I-80 Freeway re-construction

  • Start Date: Mid-May 2021
  • Update: Construction is moving forward with the traffic now moved to the center of the roadway while work on the outside lanes between 1500 E. and 2300 E. continues. The 20th East bridge replacement is now in complete, and work on the 17th bridge continues. Expect work to begin on the 1300 East bridge this fall.
  • Completion: Spring 2023
  • Project Description: UDOT will be replacing 50+ year old, worn out, pavement from 1300 East to 2300 East. The project will also include replacing brides at 1300, 1700, and 20000 East.
  • Project Location: 1300 East to 2300 East.

The 21s

  • Start Date: Mid-June 2021
  • Update: Construction is fully underway on the site. The sidewalk has been re-opened to east/west pedestrian access along the block face between 21-2200 East.
  • Completion: Spring 2023
  • Project Description: Multi-unit r
  • Location: 2000 E./2100 S.

900 E./Sugarmont Project

  • Start Date:
  • Update: Demolition is complete and the site is being prepared for construction.
  • Completion: Summer 2023.
  • Project Description: 4-Story, 45-unit apartment building.
  • Location: Approx. 2200 S./900 E.

Hawk Light Signal Project

  • Start Date: November 17, of 2021.
  • Update: Completed!
  • Completion: March 25, 2022.
  • Project Description: This is the last item on the current list of several safety additions to the Sugar House CBD area made over the last two years.
  • Location: Approximately 2150 S. /Highland Drive

 

New Projects Coming Soon

McClelland Street

Start Date: First week of May 2022.

Est. Completion: Mid summer 2022.

Project Description: Resurfacing and adding complete street refinements to McClelland Street between 2100 S. and

Sugarmont Drive.

2100 South Sewer/Water Line Replacement Project

  • Start Date: MidJuly 2022.
  • Completion: Late summer 2022.
  • Location: 2100 South/1100 East- 2100 South/ Yuma Street.

Former Snelgrove Ice Cream property

  • Start Date: July/August 2022.
  • Update: Demolition of the old structures on site is completed and construction is set to begin mid-summer.
  • Completion: Mid 2024.
  • Project Description: Mixed use residential.
  • Location: 2100 S./800-900 E.

Alta Terra (Former 24 Hour Fitness

  • Start Date: Spring, April/May, 2022.
  • Update: This project is set to begin within the next two weeks.
  • Completion: Spring 2024.
  • Project description: Residential (Approx. 340 units)
  • Location: Ashton Ave./1100 E.

For questions or reporting issues or concerns contact: Bill Knowles, SLC Community Ombudsman: 801-580-2626; Knowles.bill@att.net

@dmin
tech@sitesbysara.com