29 Nov Sugar House Construction Projects
Sugar House Construction Projects
Updated report
December 29, 2025
Montaire (Formerly Alta Terra) (Formerly 24 Hour Fitness)
Location: Ashton Ave./1100 E.
Start Date: June 2022.
Est. Completion: Spring 2026.
Project description: Residential (Approx. 340 units)
Update: The south building is completed and currently receiving occupants. Inquiries
into availability and rental information can be directed to: montaireliving.com.
The full external structure is now completed and framing is progressing inside the north
building. Brick is now being installed on the outer walls. Through traffic between Ashton
Ave. & 1100 East remains open in both directions. Expected project completion is spring
- Parking will remain available along the park frontage on 1100 East. 2 Hour
Parking signs have been installed at the east end of Fairmont Park as well as “No
Construction Parking” signs to discourage all-day parking by construction workers and
are now placed on the east end of Ashton Ave and to the entrance to the dog park.
Fairmont Heights Project (formerly York Building)
Location: 2450 S./1100 E.
Start date: December 2025.
Est. Completion: Early 2028.
Project description: Residential, affordable senior living (175 units).
Update: The demolition process of the old building is now underway and construction
will follow in early spring.
Coming Attractions
The former Deseret Industries at Highland Drive/Sugarmont, demolition
occurring late ‘25.
S Line extension project beginning early ‘26.
For questions or reporting issues or concerns contact: Bill Knowles, SLC Community
Ombudsman: 801-580-2626; [email protected]