29 Nov Sugar House Construction Projects
Updated report
September 22, 2025
Montaire (Formerly Alta Terra) (Formerly 24 Hour Fitness)
Location: Ashton Ave./1100 E.
Start Date: June 2022.
Est. Completion: Early Spring 2026.
Project description: Residential (Approx. 340 units)
Update: The south building is completed and currently receiving occupants. Inquiries
into availability and rental information can be directed to: montaireliving.com.
The full external structure is now completed and framing is progressing inside the north
building. Through traffic between Ashton Ave. & 1100 East remains open in both directions.
Expected project completion is early spring 2026. Parking will remain available along
the park frontage on 1100 East. 2 Hour Parking signs have been installed at the east
end of Fairmont Park as well as “No Construction Parking” signs to discourage all-day
parking by construction workers and are now placed on the east end of Ashton Ave.
2100 South Road Re-construction Project
Location: 2100 South, 700 East-1300 East.
Start Date: Early March. 2024
Est. Completion: Fall 2025.
Project Description: Installing updated water and sewer lines and re-building long
worn-out roadway, improving pedestrian crossing, and traffic calming.
Update: Replacement of the roadway is now completed on both sides of the road
between 700 East and 1100 East and two-way traffic is now open on both east and
west bound lanes from 700 to 1300 E. Some work continues on landscape
improvements and is expected to be completed, as is the rest of the project, by end
of September, six weeks ahead of schedule.
1300 East Roadway Repair Project
Location: 1300 East from 2100 S.-3000 S.
Start Date: April 21, 2025.
Est. Completion: Fall 2025.
Project Description: Roadway repair and re-paving, crosswalk improvements.
Update: Work continues between 2100 S. and the freeway exits/entrances and
is being restricted to night time only, 8:00 p.m. – 6:00 a.m., to better
accommodate the heavy volumes of traffic in those areas. The intersection at
2100 S./1300 E. will be closed during overnight hours Sunday – Friday, as well as
either north or south bound traffic on 1300 East, depending on which half crews
are working on. This section of work is expected to last 3-4 weeks.
Coming Attractions
The former Deseret Industries at Highland Drive/Sugarmont, demolition
occurring late fall ‘25.
The York Building, Simpson Ave./1100 E., demolition occurring late ‘25/early ‘26,
new apartment construction early ‘26.
S Line extension project beginning early ‘26.
For questions or reporting issues or concerns contact: Bill Knowles, SLC Community
Ombudsman: 801-580-2626; [email protected]