29 Nov Sugar House Construction Projects
Sugar House Construction Projects
Sugar House Construction Projects
Updated report
July 29, 2025
Montaire (Formerly Alta Terra) (Formerly 24 Hour Fitness)
- Location: Ashton Ave./1100 E.
- Start Date: June 2022.
- Est. Completion: Early Spring 2026.
- Project description: Residential (Approx. 340 units)
- Update: The exterior and interior work on the south portion of the project is completed and the unit is still awaiting final inspections to be approved before opening in early August. Inquiries into availability and rental information can be directed to: montaireliving.com. The full height has now been reached and framing is progressing inside the north building. Through traffic between Ashton Ave. & 1100 East is now open in both directions. Parking will remain available along the park frontage on 1100 East. 2 Hour Parking signs have been installed at the east end of Fairmont Park as well as “No Construction Parking” signs to discourage all-day parking by construction workers and are now placed on the east end of Ashton Ave.
2100 South Road Re-construction Project
- Location: 2100 South, 700 East-1300 East.
- Start Date: Early March. 2024
- Est. Completion: Fall 2025.
- Project Description: Installing updated water and sewer lines and re-building long worn-out roadway, improving pedestriancrossing, and traffic calming.
- Update: Replacement of the roadway is now completed on both sides of the road between Lincoln St. and 700 East. Two-way traffic is now open on both east and west bound lanes. Some work continues on landscape improvements and intersection crosswalks and is expected to be completed by mid-to-late August. Traffic between 900-1100 E. is reduced to one way only, westbound, for a period of three to four more weeks, with detours required for eastbound traffic at 900 E. as the old road is taken up and replaced with new pavement. Two way traffic remains on target to be re-opened by mid August.
1300 East Roadway Repair Project
- Location: 1300 East from 2100 S.-3000 S.
- Start Date: April 21, 2025.
- Est. Completion: Fall 2025.
- Project Description: Roadway repair and re-paving, crosswalk improvements.
- Update: Work continues along various locations along the 13th East corridor. Work occurring between 2100 S. and the freeway exits/entrances will be restricted to night time only, 8:00 p.m. – 6:00 a.m., to better accommodate the heavy volumes of traffic in those areas, and is expected to begin in late August.
- Work was recently completed at the intersection of 1300 E./2100 S. replacing pedestrian ADA ramps at all four corners.
- Work was also completed at the intersection of 1300 E./Highland Drive, a week ahead of schedule, and the intersection is now fully re-opened to traffic.
For questions or reporting issues or concerns contact: Bill Knowles, SLC Community Ombudsman: 801-580-2626; [email protected]