900 East Update

900 East Update

900 East Reconstruction Project
Traffic Alert
Starting Thursday, July 15th, crews will be milling (removing old asphalt) in the center lane from 2100 South to 2700 South. There will be temporary access ramps to maintain side street access. There will be no access restrictions to businesses.
On Saturday, July 17th, crews will be paving the center lane from 2100 South to 2700 South. Drivers are asked not to drive over the new asphalt for 30 minutes to allow for cooling time.
Again, we appreciate your patience and flexibility. Feel free to reach out to the project team with any questions or concerns you have. Thank you!
Salt Lake City Engineering is reconstructing 900 East from Hollywood Avenue to 2700 South. Construction began on May 3, 2021, with anticipated completion Fall 2021.
Things to Keep in Mind
Crews will be maintaining work zones on each side of the roadway. These traffic shifts will be ongoing throughout construction season.
  • Construction activities Monday through Friday between 7 am and 7 pm
  • Increased noise, vibrations, and dust
Parking & Access
  • On-street parking will be restricted at all hours during construction. Cars remaining in the construction zone will be towed at owners expense.
  • Residential and business access will be maintained
  • A number of driveway approaches and curb and gutter segments will be repaired with this project
  • Crews will notify impacted residents before access to driveways is restricted due to construction activities
Traffic & Safety
  • One lane of traffic will be maintained in each direction. Medians and shoulders on the roadway will be closed throughout construction.
  • Drivers are encouraged to use 700 East or 1100 East as an alternative route
  • Travelers in the area are advised to follow instructions from signs, flaggers and equipment operators
  • 24-hour notice will be provided prior to any utility service interruption.
Other Area Projects
  • East-West Water Line Project – Salt Lake City Department of Public Utilities will be installing a large diameter water line from Forest Dale Golf Course along 900 East to Ashton Avenue. This work is anticipated to begin in May.
Please reach out with any questions or sign up for email updates!
Hotline: 801-210-8433
If you give us a call or email us, we will respond within 24 business hours.
Thank you